Do you need an HDB renovation permit? Hacking, replacing tiles, false ceilings and windows do. Painting, vinyl and gypsum partitions do not. Here is the full picture.

Updated 21 Nov 2026 · 6 min read

Key facts

  • Every renovation in an HDB flat must be done by a contractor listed in HDB's Directory of Renovation Contractors (DRC).
  • A permit is needed for hacking, replacing floor or wall tiles, false ceilings, window replacement and moving a doorway.
  • No permit is needed for painting, vinyl flooring, gypsum partitions, wallpaper or a non-fire-route main door.
  • Noisy work is allowed only from 9am to 5pm on weekdays.
  • The DRC contractor applies for the permit online, after you authorise it.
On this page
  1. Do I need an HDB renovation permit?
  2. Which renovation works need an HDB permit?
  3. Who is allowed to do HDB renovation work?
  4. How the permit application works
  5. HDB renovation rules that catch owners out
  6. Check before you sign with a contractor
  7. Why the contractor you choose matters

Do I need an HDB renovation permit?

It depends on the job, not on the size of the renovation. HDB sorts works into those that need a permit and those that do not, and the table below is a summary of HDB's building works guidelines. If your job is not in the table, ask HDB or the contractor before work starts.

The permit lets HDB check the planned works before they begin, not after. Together with HDB's rules, it limits what can be hacked, how thick new floor and wall finishes can be, and when noisy work may happen.

Which renovation works need an HDB permit?

A summary of HDB's building works guidelines. The permit is applied for by the contractor, and your flat's details can change the answer.

WorkPermit?What to know
Hacking walls, partial or completeYesNeeds HDB's written approval first. Structural walls cannot be hacked.
Replacing floor tiles or other floor finishesYesFloor finish and screed together must stay within 50 mm.
Replacing wall tiles or wall finishes up to the ceilingYesWall finishes and plaster must stay within 25 mm.
Toilet or bathroom floor and wall finishesYesNot allowed in the first 3 years after the block is completed.
Installing a false ceilingYesSome materials and clearances are set by HDB.
Replacing windowsYesDone by a BCA Approved Window Contractor who is also in HDB's directory.
Main door on a fire-escape routeYesMust be a half-hour fire-rated door.
Painting, wallpaper and plasteringNoSpray painting and plastering are in HDB's no-permit list.
Laying vinyl, carpet or linoleumNoLaid over the existing floor, with no hacking.
Gypsum partition wallNoA 63 mm hollow block wall or an 80 mm glass block wall also needs none.
Main door that is not on a fire routeNoReplacement of door and frame.

Rules change. Check HDB's current guidelines, or ask us, before you start.

Who is allowed to do HDB renovation work?

Under HDB's renovation control rules, flat owners may only engage contractors listed in HDB's Directory of Renovation Contractors (DRC). If you do not, you can be prosecuted. So can a contractor who is not on the list but carries out the work, or presents themselves as a listed contractor. HDB's wording covers renovation in general, so if you are unsure whether a small job without a permit still needs a listed contractor, ask HDB.

Being listed does not mean HDB endorses a contractor. HDB says hiring is a private contract between you and the contractor, and it points owners to CASE's guides, fair-trading tips from CCCS and CaseTrust-accredited contractors. Check a contractor on HDB's directory yourself, and ask for the name of the firm that will apply for your permit.

Before you sign, ask for the firm's name and check it in the directory. The firm on the contract should be the one that applies for your permit.

Some trades add another licence. A PUB Licensed Plumber does water and sanitary work, an EMA Licensed Electrical Worker (LEW) does wiring, an EMA licensed gas service worker does gas work and a BCA Approved Window Contractor replaces windows. Simple plumbing tasks can be done by a handyman, as PUB allows.

How the permit application works

The contractor, not you, applies for the permit, using HDB's electronic system. You authorise the contractor to submit the application, and the contractor attaches a form that you have signed. For works that HDB evaluates, such as taking down a wall, a floor plan is attached. HDB may require a Qualified Person, a professional engineer, to supervise some demolition.

Do not let work begin before the permit is approved, even for a small job such as removing a few tiles. HDB can require unauthorised work to be removed, or charge an administrative fee if it allows the work to stay. Keep a copy of the permit and display the notice of renovation outside your flat while the work is on.

When you have a permit, the clock starts: renovation in an existing block must finish within one month of the permit date, and within three months in a newly completed block. Window-only works have two weeks.

HDB renovation rules that catch owners out

  • Hours. General renovation is allowed 9am to 6pm on weekdays and Saturdays. Restricted work, such as wall demolition, removing floor or wall finishes, tile cutting and heavy drilling, is allowed only 9am to 5pm on weekdays. See our guide to HDB renovation hours.
  • Neighbours. HDB asks you to give written notice to neighbours within two units, five days ahead.
  • Waterproofing. Toilets need a waterproofing screed and a membrane before new finishes, turned up at least 150 mm at the walls.
  • Debris. It must not go down the refuse chute, the squat pan or a floor trap.
  • Disallowed works. Hacking structural members, raising the floor more than 50 mm with concrete and replacing full-height windows are not allowed.
  • Windows and main doors. Every window replacement needs a permit and a BCA Approved Window Contractor in HDB's directory. Replacing full-height, three-quarter-height and bay windows is not allowed, except for damaged frames. A main door on a fire-escape route must be half-hour fire-rated with a self-closing frame.
  • Overlay tiling. Laying tiles over one existing layer, with no hacking and no screed, is described by HDB as not needing a permit. Confirm with HDB whether you still need a DRC contractor for it. See also our guide to tiling.

Check before you sign with a contractor

  • Look the firm up on HDB's Directory of Renovation Contractors.
  • Ask who applies for the permit, and when it will be approved.
  • Get a written quote that lists the works, materials and payment stages.
  • Ask what deposit is required. CaseTrust-accredited firms cap the first deposit at 20% of the contract price.
  • Ask who does the plumbing, electrical and window work, and whether they are licensed.
  • Keep a copy of the permit, the quote and every payment receipt.

Why the contractor you choose matters

CASE received 787 complaints about renovation contractors in 2025, which made it the fourth most complained-about industry, and CASE also counts the money consumers lose on renovation prepayments. A permit does not protect you from that, but a clear contract and a small first deposit help.

We do not hold HDB's listing ourselves. Our HDB-registered contractor does the permit works, signs the contract for them and applies for the permit. We coordinate and stay your contact. Work that needs no permit, such as repainting, is usually done by our own team; where HDB's rules call for a listed contractor, our HDB-registered contractor does it instead. If you are planning a renovation, see our renovation page, or WhatsApp us a photo of the flat. Doors and windows have their own page on doors and windows.

Frequently asked questions

Do I need a permit to replace my floor tiles?

Yes, for replacing tiles or other floor finishes. Laying vinyl over the existing floor does not need one. The contractor applies for the permit after you authorise it.

Can I hire any contractor for HDB renovation?

No. HDB requires a contractor listed in its Directory of Renovation Contractors. The flat owner and the contractor can both be prosecuted if the work is not done by a listed one.

What happens if I renovate without a permit?

HDB can ask you to remove the unauthorised work, or charge an administrative fee if it lets the work stay, and it may prosecute for unauthorised hacking.

Does painting my flat need an HDB permit?

No. Painting, wallpaper and plastering are in HDB's no-permit list. The work still has to follow the renovation hours.

Can I renovate my toilet in a new BTO flat?

Not by removing the old finishes in the first 3 years after the block is completed. HDB does not allow the toilet's wall and floor finishes to be removed in that period.

Send a photo. Get a fixed price.

WhatsApp us a photo or a short video of the problem, with your postal code. We reply with a price the same working day.

  1. Send a photoWhatsApp us a photo or a short video of the problem, with your postal code.
  2. Get a fixed priceWe reply with a price, or book a visit when a job needs a look first.
  3. We fix itThe right tradesman for the job arrives in the time slot you booked.
  4. Pay when it's donePay by PayNow or card after the work is finished and you have checked it.